fbpx

Formulae Notes

Note that back in the days, you would have to know the formulas by heart. One would get many questions in the exam, which would require one to be good with numbers. However now a days in the newer version of PMP, the focus is shifted from calculations to understanding what the formula implies. you might see some questions like “what does it mean if the CPI is Positive and SPI is negative?”.

So don’t focus much on remembering all the formulas, rater focus on what the formula means for the project performance.

Budget at Completion: Assigned project budgetBAC = total project budget
Earned Value: Value earned in the work completedEV = BAC x % complete
Planned Value: Assigned value of the work to be completed as of the status datePV = Budgeted value of the work to be completed
Schedule Variance:
0 = on schedule
Negative = behind schedule
Positive = ahead of schedule
SV = EV – PV
Schedule Performance Index:
1 = on schedule
< 1 = behind schedule
1 = ahead of schedule
SPI = EV / PV
Actual Cost: Actual cost of the work completed as of the status dateAC = what has been spent
Cost Variance:
0 = on budget
Negative = over budget
Positive = under budget
CV = EV – AC
Cost Performance Index:
1 = on budget
< 1 = over budget
1 = under budget
CPI = EV / AC
To-Complete Performance Index:
Efficiency ratio comparing work remaining (BAC-EV) to money remaining.
Money remaining may be based on the budget (BAC) or the forecast (EAC).
IF TCPI is >1 then its bad reflecting more work remaining than money available.
TCPI = (BAC-EV) / (BAC-AC)
TCPI = (BAC-EV) / (EAC-AC)
Estimate at Completion: A forecast of the estimated total project spend at completionEAC = AC + ETC (bottom-up)
EAC = AC + BAC – EV
EAC = BAC / CPI
EAC = AC + [(BAC – EV) / (CPI x SPI)]
Estimate to Complete: A forecast of the estimated cost remaining to complete the projectETC = new estimate
ETC = EAC – AC
Variance at Completion: The difference between the budget and the forecastVAC = BAC – EAC
Communication Channels: The number of communication channels or paths on your projectn (n – 1) / 2
Lead: Acceleration of a successor activityActivity Duration – Lead
Lag: Delay of a successor activityActivity Duration + Lag
Three point Estimation triangular: Used for Duration and cost estimation(Optimistic + Most Likely + Pessimistic ) / 3
Three point Estimation Beta/PERT: Used for Duration and cost estimation(Optimistic + (4 X Most Likely) + Pessimistic) / 6